Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
OffshoreWind.biz reports on 7 September 2022 that Nexans has completed installation of all subsea and onshore export cables for the 1,075 MW Seagreen project, noting that installation of the offshore export cables "commenced at the beginning of this year" (i.e. early 2022). This confirms that Stage 5 (subtidal export cable installation) for the Seagreen Offshore Transmission Assets started in early 2022, broadly in line with the original plan for Q1 2022.