By 20 December 2023, Seagreen Wind Energy Limited confirmed that the final length of rock protection installed over the Seagreen export cables was 44.3 km, consistent with the approximate maximum set out in the Offshore Transmission Asset Cable Plan, indicating completion of export cable and associated protection installation and prompting Marine Directorate–LOT to request a marine licence variation to align the licence parameters with the as‑built transmission assets.