Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore construction for the Seagreen 1A project is planned to commence around April 2023, when Seagreen 1A Limited will start the marine works for a single high-voltage export cable from the Seagreen project area to mean high water springs at Cockenzie, under an indicative construction programme running through Q2 2024.