Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Following receipt of a 360 MW grid connection offer from National Grid for the Cockenzie substation in early 2020, Seagreen 1A accepted the offer in June 2020, securing a grid connection agreement with a target connection date of October 2023 for exporting power from up to 36 turbines.