Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Marine Scotland Seagreen 1A Screening Report Appendix A (Habitats Regulations Appraisal), Table 1-1 “Summary of key milestone dates for Seagreen 1A”, lists “Foundation, auxiliary infrastructure and inter array cabling installation” with Start date 01/01/2030 (Finish shown as 31/06/2030). This is treated as the start of the foundation installation campaign for Seagreen 1A offshore works.