Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Marine Scotland Seagreen 1A Screening Report Appendix A (Habitats Regulations Appraisal), Table 1-1 “Summary of key milestone dates for Seagreen 1A”, shows the offshore works window running 01/01/2030 to 31/07/2031 and “WTG Installation” finishing 31/07/2031. This implies completion of offshore build by 31/07/2031; recorded as a developer-provided schedule date for first power (at end of offshore works/WTG installation) by 31/07/2031.