National Grid submitted the Environmental Impact Assessment material for Sea Link as part of its Development Consent Order (DCO) application in March 2025. The submission bundled the Environmental Statement / supporting environmental information (building on earlier PEIR material) covering topics such as ecology, landscape & visual, water environment, noise, traffic, cultural heritage and mitigation measures, and formed the formal EIA package for statutory examination by the Planning Inspectorate.