Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 15 November 2010, Prysmian reported successful completion of commissioning for the first phase (Pole 1) of the SAPEI HVDC submarine link, including after‑laying electrical tests at the Latina converter station, confirming that the first pole was ready for operational service.