Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
On 5 March 2013, the German Federal Network Agency (Bundesnetzagentur) issued a decision in case BK6-13-031 concerning the Sandbank offshore wind project. The proceeding is described as a determination procedure for the allocation of connection capacity on the SylWin1 offshore grid connection for the project "Sandbank" operated by Sandbank Offshore Wind GmbH. This decision formally assigned offshore grid connection capacity to Sandbank on the SylWin1 link, clarifying and securing its transmission access arrangements within the regulated German offshore grid regime.