Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
On 15 May 2024, the European Commission’s first PCI/PMI list under the revised TEN-E framework confirmed the interconnection between mainland Italy, Corsica and Sardinia (currently known as SACOI 3) as electricity PCI 1.10, describing it as an under-construction 400 MW HVDC link replacing SACOI 2, with planned commissioning by 31 December 2027.