Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
For the SACOI 3 HVDC interconnector, Terna plans to begin offshore installation and protection of the pole and electrode marine cables in two installation campaigns starting in the second quarter of 2026, using a Prysmian cable-laying vessel (currently identified as Giulio Verne), with activities continuing through the fourth quarter of 2026.