Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
All three 237 km submarine HVDC cables for the ROMULO interconnection between Santa Ponsa Bay (Majorca) and Sagunto (Valencia) were fully laid by mid-April 2011. Cable 1 was laid by Giulio Verne starting 13 January, cable 2 by Skagerrak starting 27 January, and cable 3 by Giulio Verne starting 28 March 2011. Each cable took approximately 2 weeks to lay. Testing began over summer 2011 ahead of commissioning in Q4 2011.