Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Turbine commissioning and system testing at Robin Rigg began in August 2009 and continued through to February 2010, progressing from initial operation of the first turbine to full commissioning of all units prior to commercial operation in April 2010.