Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Installation of subsea cables for the Robin Rigg Offshore Wind Farm started in July 2008, with 64 inter-array cables connecting the turbines in four 15‑turbine loops to two offshore substations and two 132 kV export cables forming the grid connection to shore near Seaton, Cumbria.