Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Export cable installation for Robin Rigg commenced in 2009. Prysmian supplied two 132 kV export cables, each approximately 12.5 km long, connecting the offshore substation in the Solway Firth to the onshore substation at Seaton in Cumbria. Cable jointing was completed in Q3 2009.