Ofgem’s cost assessment for the Robin Rigg transmission assets records that, after Oceanteam Power and Umbilical failed to complete its reduced scope, Subocean Group was appointed to install the export cables and completed installation of the Robin Rigg West (RRW) export cable in April 2009.