MT Højgaard A/S installed all 25 monopile foundations and transition pieces at the Rhyl Flats Offshore Wind Farm using the heavy-lift vessel Svanen, supported by ~15 auxiliary vessels. Foundation works ran April–July 2008 with approximately 120 offshore and 40 onshore personnel mobilised from Port of Mostyn.