Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
The Rampion Offshore Wind Farm exported its first electricity to the UK national grid on 26 November 2017, after the first of its 116 turbines began generating power. This milestone followed completion of turbine installation, burial of 144 kilometres of array cables, and commissioning of both the offshore substation and the onshore substation at Twineham, marking the project’s transition from construction towards full operation.