Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
The installation of inter‑array cables at Rampion commenced in August 2016, when Fugro’s subsea construction vessel Fugro Symphony began transporting approximately 75 km of cable to the offshore site as part of the first phase of a two‑season programme to lay and bury 122 array cables using Fugro Symphony and Fugro Saltire with a Q1400 trenching system.