Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Overall construction of the Rampion project, including the onshore transmission assets such as approximately 27km of 150kV onshore export cables to a new substation at Twineham and the 400kV connection into National Grid’s Bolney substation, started in September 2015. These works formed the onshore construction start for the Rampion offshore transmission system that was later transferred to the Rampion OFTO.