Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Race Bank’s offshore transmission assets reached first power earlier than planned, with electricity transmission commencing one month ahead of the original schedule; this earlier-than-expected energisation affected the Interest During Construction (IDC) calculations used in Ofgem’s assessment of the project’s transmission asset costs.