Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
Jan De Nul completed the construction and float-out of all 23 massive concrete caisson structures that will form the base of Princess Elisabeth Island, marking the end of onshore fabrication at the Vlissingen yard. The caissons, which constitute the physical backbone of the artificial energy island, have been moved to the Scaldia terminal for finishing works ahead of the next offshore installation phase in the North Sea.