Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Pre-installation surveys for Pentland, planned for 2025/26, will comprise ROV-based visual inspections of mooring locations and cable routes, potentially supplemented by multibeam echo sounder, to confirm exact routing and seabed preparation needs in the main offshore site between April and October of the survey year.