Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
In June 2023, alongside granting Section 36 consent, Scottish Ministers approved the offshore consents for the Pentland Floating Offshore Wind Farm, including marine licences for the wind farm structures and export transmission infrastructure. These marine licences allow installation of the floating turbines, anchors, mooring systems, inter-array cables and offshore export cables for the approximately 100 MW project off Dounreay.