Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Mobilisation of offshore vessels and start of foundation installation works on the 1.5 GW Outer Dowsing array, ~54 km off the Lincolnshire coast. The developer's March 2025 Landfall-Hogsthorpe Community Liaison Group (CLG) update targeted offshore works commencement in 2027, contingent on revenue support. The project was unsuccessful in AR7, so first steel in water defers until after AR8 closure (~Q3-Q4 2026 results) and a subsequent FID. Year precision; deferred 12 months from the developer's pre-AR7 statement.