Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
By September 2024, Outer Dowsing Offshore Wind had incorporated seabed and aggregate‑licensing constraints into its offshore export cable corridor design by retaining route optionality to avoid crossing the Inner Dowsing sandbank, where The Crown Estate had extended an aggregate extraction option over area 1805 and a Marine Licence application for extraction over the whole site had been submitted to the Marine Management Organisation. These mapped constraints informed definition of the Order Limits and export cable alignment for the Development Consent Order application.