Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
As part of the Ostwind 3 grid connection project, the steel substructure (jacket) for the Jasmund offshore platform, manufactured at a shipyard in Vlissingen in the Netherlands, was shipped to the Baltic Sea at the beginning of December 2025 and then deeply anchored in the seabed using steel piles off the island of Rügen.