Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In a January 2026 update on the Ostwind 3 grid connection project, 50Hertz reported that installation of the approximately four‑kilometre onshore cable route between the Vierow landing point and the new Stilow substation in the Vorpommern‑Greifswald district has been completed, finalising the land section of the export cable system.