Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In October 2022, 50Hertz awarded Hellenic Cables a turnkey contract to design, supply, store, install, joint, terminate, test, and commission the Ostwind 3 export cable system, comprising 105 km of 220 kV subsea three-core export cable, 13.5 km of 220 kV onshore export cable, and 2 km each of 220 kV and 66 kV platform cables to connect the Windanker offshore wind area to the German extra‑high voltage grid.