Equinor’s 7 October 2024 project status update for “Oseberg gas phase 2 and power from shore (OGP)” states that due to longer delivery times for transformers and increased complexity, “Planned commissioning has been postponed from 2026 to late 2027.” This commissioning timeline is used as the best available developer guidance for the offshore power-from-shore facilities (including the offshore substation) on the Oseberg project. Following the rules for vague timeframes, “late 2027” is represented as 2027-12-31 with quarter-level precision.