Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
The main phase of inter-array cable installation at the Ormonde Offshore Wind Farm was completed by June 2011, concluding the campaign to lay the cables between turbines and the offshore substation, with additional burial works on some sections carried out later in November and December 2011.