Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Areva was selected to design and build the 132 kV onshore substation at Heysham that transfers electricity from the Ormonde export cable into the UK national grid, providing the onshore grid interface for the Ormonde offshore transmission system.