For the Upgrade of the Öresund connection between Sweden and Denmark, NKT completed testing, commissioning and energizing of the around 9 km 400 kV HVAC offshore and onshore cable system within the project’s 2019–2020 schedule, confirming that system testing and commissioning of the replacement cables were finished by 2020.