Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Energinet Eltransmission A/S concluded a works contract titled "400 kV offshore installation for Øresund 2" with JD Contractor A/S on 11 September 2024 for installation of a reinvestment 400 kV cable system of three single-core cables between the transition stations Skibstrupgaard (SKB) in Denmark and Kristinelund (KLD) in Sweden. The award is recorded in EU contract award notice 587834-2024 (OJ S 191/2024) for the lot covering offshore installation and associated works.