For Energinet’s planned replacement of the existing 400 kV cable system across the Øresund, Deep’s surveying team, working with Ramboll, completed a marine route survey along the cable corridor. Using the vessel Deep Seapal equipped with dual‑head multibeam echo‑sounder, side‑scan sonar and magnetometer, they collected seabed and sub‑seabed data over a 16‑day campaign and delivered processed results and interpretations to Energinet.