Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Hellenic Cables signed a contract with Danish TSO Energinet to supply the 400 kV AC interconnection cable system between Denmark and Sweden, part of the Øresund 400 kV link. Under the agreement, Hellenic Cables will design, manufacture and deliver about 30 km of submarine and 12 km of underground single‑core 400 kV cables, and will supervise installation, testing, jointing and termination, with production starting in 2023 and deliveries expected in the first half of 2024.