On 14 August 2024, the Poseidon Wind Energy project company, Poseidon Wind Energy S.r.l., entered the national VIA (Environmental Impact Assessment) procedure for a 1008 MW floating offshore wind farm in the north‑western Tyrrhenian Sea more than 40 km off Olbia. The project appears in the Italian Valutazioni e Autorizzazioni Ambientali (VIA‑VAS‑AIA) register under the PNIEC‑PNRR ‘Provvedimento Unico in materia Ambientale’, with the procedure status shown as being in technical review (istruttoria tecnica), indicating that the EIA application has been formally submitted and is under assessment.