Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
On 15 November 2024, Odra Energia submitted project integration documents to MASE and MiC as part of the ongoing VIA process, responding to requests from MASE, ISPRA and public observations. The updated package reduced the number of turbines from 90 to 73, lowered the maximum capacity, and increased the minimum distance from the coast from 12 to 14 kilometres to lessen visual and seabed impacts.