On 15 November 2024, Odra Energia submitted project integrations that substantially optimised the offshore layout, reducing the number of turbines from 90 to 73 and capacity from 1,325 MW to 1,095 MW, moving the closest turbines from 12 km to 14 km offshore by removing the two inshore rows, adopting semi-taut moorings, increasing spacing between export cable circuits, committing to bury inter-array cables, and adjusting turbine positions and landfall works to limit visual and seabed impacts and avoid seabed pockmarks.