Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore construction start projected for 2028 using the COD-minus-2-years heuristic anchored to the LanWin2 (NOR-12-2, TenneT) grid system IBN 2030. Offshore wind-farm construction typically begins ~2 years before COD — foundation installation, then turbine installation, then commissioning sequenced to finish ahead of grid availability. Subject to FID, supplier selection, vessel availability and supply-chain status. Date precision is year-level given the planning-stage maturity.