Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In late October 2016, the offshore high-voltage substation (OHVS) at the Nobelwind offshore wind farm was powered for the first time, following its installation on site a month earlier, marking a key grid-connection and system energisation milestone for the project.