Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
In July 2015, DeepOcean 1 UK Ltd announced that offshore site-preparation activities for the Nobelwind (Bligh Bank Phase II) offshore wind farm, including pre-lay surveys, pre-lay grapnel runs and foundation preparation for cable pull-ins, were scheduled to start in the third quarter of 2016 and continue into the fourth quarter, ahead of and alongside inter-array cable installation and trenching between the turbines and the Nobelwind offshore high-voltage substation, and a coupling cable to the Belwind I substation.