Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 22 September 2016, Jan De Nul installed the last monopile foundation at the Nobelwind offshore wind farm, completing the installation of all 51 pile foundations for the 50 turbines and the offshore high-voltage substation on Bligh Bank.