Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 28 September 2015, Jan De Nul Group signed an engineering, procurement, construction and installation (EPCI) contract for Nobelwind to design, procure, build and install 51 monopile foundations for 50 turbines and the high-voltage substation, as well as scour protection and turbine installation, with Ostend selected as the marshalling harbour and offshore works scheduled from April 2016 to completion in 2017.