Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore works to install and trench Nobelwind’s subsea power cables began in the third quarter of 2016, when DeepOcean started offshore execution of its inter-array and coupling cable contract, including installation and burial of 50 inter-array cables and a 33 kV coupling cable between the Nobelwind and Belwind I offshore high-voltage substations at the Bligh Bank site off Zeebrugge.