Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
DeepOcean’s July 2015 project announcement stated that the offshore execution phase of its Nobelwind contract, including installation and trenching of 50 inter-array cables, installation and trenching of the coupling cable between the Nobelwind and Belwind I offshore substations, and associated seabed works, was planned to start in Q3 2016 and run into Q4 2016, with only optional cable termination and testing potentially extending into Q2 2017, implying that the main offshore cable-laying campaign was scheduled for completion by the end of 2016.