Northern Aegean Interconnection Phase B : Lesvos - Chios
November 2023
Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
In November 2023, IPTO assigned contracts for studies and marine seabed surveys for the Northeast Aegean islands electrical interconnections, and by April 2024 reported that seabed surveys were already completed or in progress on several Northeast Aegean routes, marking the start of the marine geophysical survey campaign for the wider North‑East Aegean interconnection programme that includes the planned Lesvos–Chios 150 kV AC cable link.