Northern Aegean Interconnection Phase B : Lesvos - Chios
December 2024
Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
IPTO later confirmed that the marine surveys for both the Dodecanese and the Northeastern Aegean electrical interconnections were completed in December 2024, signalling the conclusion of the seabed investigation and routing work for the submarine cable corridors of the North‑East Aegean interconnection, including the future Phase B Lesvos–Chios 150 kV AC link.