Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
On 3 January 2020, IPTO announced that the Interconnection of the North Aegean Islands would be included in its preliminary Ten‑Year Network Development Plan (TYNDP) 2021‑2030, launching the project in parallel with the Dodecanese interconnection. Phase A of this plan explicitly covers the Nea Santa–Lemnos HVC and the Lemnos–Lesvos interconnections, with completion then targeted for 2027, formally placing the Limnos–Lesvos HVAC subsea link on Greece’s regulated transmission development roadmap.