Approximately 70km of 33kV aluminium AC subsea inter-array cables connecting turbines to the offshore high-voltage station; Van Oord contracted for BoP including inter-array cable installation.
Van Oord was contracted for balance-of-plant works on the Norther offshore wind farm. Its scope included offshore installation activities covering the wind farm’s inter-array cable system (in addition to other BoP packages mentioned in the source).